The material supply for this project is complex in nature. The building has east and west towers, each consisting of different primary and accent colors as well as three distinct panel finishes (Smooth, Grooved, and Stripy). This configuration resulted in 6 different panel types. The project required 63 different lengths of panels for a total of almost 27,000 individual panels. The panels are installed in various random patterns according to the architect’s vision.
Completion: 2015
Architect: Bruner/Cott
Installer: Cheviot Corop
General Contractor: Suffolk
Material: K20 Custom Colors
Finish: Flat, Grooved, Stripy
Quantity: 61,000 Sq Ft